top of page
Montgomery X Pitt.png

425 Montgomery Project

Progress Schedule

425 Montgomery Monthly Schedule Narrative:

Our Projects
May 2025

In the month of May, we will continue trucking/hauling soils off-site throughout our mass excavation operations. Lagging operations for the support of excavation system will continue throughout the month. Utility work along the Montgomery Park side of N. Royal Street has since been completed. Parking along N. Royal street, against the park, is now reopened to the public. At the Northeast corner of the jobsite along N. Royal Street, excavation for permanent power feeds will be taking place at the transformer enclosure. In the last week of May/early June we plan on erecting the tower crane and start pouring concrete foundations. 

 

Please check back at the end of May for the June construction operations narrative. Thank you and have a wonderful day.

April 2025

In the month of April, we will continue trucking/hauling soils off-site throughout our mass excavation operations. Pile driving operations for the support of excavation is expected to be complete by the 1st or 2nd week of April and lagging for the support of excavation will continue throughout the month. Installation of dewatering wells/system will continue throughout the month of April. Along the Montgomery Park side of N. Royal Street utility work will be nearing completion this month. Once this utility work is completed, parking along N. Royal street, against the park, will be reopened to the public. At the Northeast corner of the jobsite along N. Royal Street, we will be pouring concrete to form the permanent retaining walls for a transformer enclosure.

 

Please check back at the end of April for the May construction operations narrative. Thank you and have a wonderful day.

March 2025

In the month of March we will begin trucking/hauling soils off-site. Pile driving operations for the support of excavation will start the week of 3/17/2025 and run into the month of April. As pile driving operations are underway we will be installing dewatering wells/system to lower the water table to allow for earthwork and foundation construction. Along the Montgomery Park side of N. Royal Street utility work is schedule to start the week of 3/10/2025. While this utility work is ongoing parking along N. Royal street will be closed during construction work hours.

​

bottom of page